June 2025 update
Construction in Coral Bay is progressing well. The first section of the Clubhouse and Reception building is expected to stand in the coming weeks, with fabrication of precast concrete elements for these structures underway and expected to be finalised shortly.
The installation of underground services is now complete, and the Workshop building is fully operational following the successful installation of the site’s sewer network and hot water plant. Road pavement works for the internal roads and car park areas have also been completed.
Main manufacturing efforts associated with the delivery of 123 modular accommodation units forming part of the resort are scheduled to commence at the end of June.
For any questions or feedback, please reach out to ningalooproject@rac.com.au or fill out the form via Get in Touch, and a project team member will respond accordingly.

Past updates
May 2025 update
Great progress continues to be made on site in Coral Bay. The installation of in-ground services including sewer, water, fire water, electrical, and communications are largely complete.
Civil works for the Clubhouse and Reception buildings along with the installation of pad and strip footings systems are progressing in line with the schedule. The workshop building is now complete, allowing for the removal of temporary site facilities.
Design documentation had been finalised and certified, enabling the last remaining building permits to be obtained.
Main fabrication of the modular accommodation units is scheduled to commence in early June 2025.
April 2025 update
The Redevelopment is advancing steadily, with significant progress achieved in recent weeks.
The Robinson Street carpark is now complete and re-opened for public use on Friday 4 April 2025. Major retaining walls have been completed, site earthworks are progressing well, and the installation of in-ground services, including sewer, water, fire water, electrical, and communications infrastructure, are continuing as planned. The Resort workshop has been completed and following its energisation (expected mid-May) will become our project site facilities to allow the removal of other temporary site offices.
In early May, we will start with detailed civil works including internal roads and car park areas. At the same time, structural works will commence with a focus on foundations to both modular accommodation blocks and the in-situ Clubhouse and Reception building.
March 2025 update
Redevelopment works are continuing, with key activities including:
Upgrade of Robinson Street carpark:
- Significant progress has occurred in recent weeks, with only footpath construction and line marking remaining.
- The road is currently on track to be re-opened ahead of the April school holidays.
Site earthworks:
- Over the coming weeks, there will be a focus on the installation of in ground services, including sewer, water, electrical and communications.
February 2025 update
Upgrade of Robinson Street carpark:
- Civil works are progressing well. New kerbing and asphalt works are currently scheduled for March 2025, with line marking and footpaths to follow soon after.
- Robinson Street road reserve will remain closed until the scheduled re-opening in April 2025.
Major retaining structures:
- Works on major retaining walls across the site are expected to continue through to the end of March 2025.
Hard digging:
- To allow building works to commence, rock must be broken out and removed from site. Rock breaking activity began in early February and is currently expected to continue until the end of February.
- We continue to do all we can to mitigate noise and dust impacts. We once again thank the Coral Bay community for your patience and understanding while these unavoidable works are undertaken.
January 2025 update
Following a short break over the festive period, works recommenced on site in mid-January. Over the coming weeks, key activities include:
Upgrade of Robinson Street carpark:
- Civil works will continue along Robinson Street. The Robinson Street road reserve will remain closed until the scheduled re-opening in April 2025.
Major retaining structures:
- Major retaining walls across the site will be constructed over the coming weeks, with completion expected in late March 2025.
Hard digging:
- To allow building works to commence, rock must be broken out and removed from site.
- Rock breaking has been scheduled for early February and is expected to last for a couple of weeks.
- This will create some unavoidable noise and vibration that will be noticeable around town.
Operating in line with the approved site and construction management plans, we will continue to do all we can to mitigate noise and dust impacts.
December 2024 update
In recent weeks, progress on site has included the installation of retaining walls. Whilst works have been completed in line with approved site management practices, windy conditions have unfortunately led to unavoidable dust and noise impacts at times.
Works during December include further retaining wall construction, along with minor civil earthworks at the rear of the property. Compaction and rock breaking works may be heard by neighbouring properties at times.
We continue to do all we can to mitigate noise and dust impacts. This includes conducting works only within approved operating hours and closely following all dust, vibration and noise management requirements.
Works on site will temporarily cease during the festive period from Friday 20 December, before recommencing in mid-January 2025.
November 2024 update
Demolition and site clearing was completed in late May 2024. Construction activity in Coral Bay was then paused as land dealings relating to acquisition and amalgamation and Lot 54 were worked through.
With the process now near completion, we have commenced procurement and contracting of various construction partners to conduct the next stages of the redevelopment.
Minor works have now recommenced on site in Coral Bay, starting with preliminary earthworks and wastewater adjustments to allow the installation of required retaining walls along the northern end (Robinson Street end) of the property.
July 2024 update
Demolition and site clearing works were completed at the end of May 2024.
Works on site in Coral Bay have been paused as we work through the next steps.
We have commenced the civil works tender process, which we continue to progress. We expect to have a civil contractor appointed and ready to recommence works on site soon.
We are also continuing to engage with the Department of Planning, Lands and Heritage (DPLH) around the finalisation of land acquisition and amalgamation.
A further update will be provided once these next steps are finalised.